Title: PUREX new substation ATR

Abstract

This document is the acceptance test report (ATR) for the New PUREX Main and Minisubstations. It covers the factory and vendor acceptance and commissioning test reports. Reports are presented for the Main 5 kV substation building, the building fire system, switchgear, and vacuum breaker; the minisubstation control building and switch gear; commissioning test; electrical system and loads inspection; electrical utilities transformer and cable; and relay setting changes based on operational experience.

Authors:
Publication Date:
Research Org.:
Fluor Daniel Hanford, Inc., Richland, WA (United States)
Sponsoring Org.:
USDOE Office of Environmental Restoration and Waste Management, Washington, DC (United States)
OSTI Identifier:
362456
Report Number(s):
HNF-SD-CP-ATR-089
ON: DE99051015; BR: EW7003000; TRN: AHC29926%%110
DOE Contract Number:  
AC06-96RL13200
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: 12 May 1997
Country of Publication:
United States
Language:
English
Subject:
05 NUCLEAR FUELS; 24 POWER TRANSMISSION AND DISTRIBUTION; HANFORD RESERVATION; FUEL REPROCESSING PLANTS; POWER SUBSTATIONS; PERFORMANCE TESTING; ELECTRICAL EQUIPMENT; SURPLUS NUCLEAR FACILITIES; MONITORING

Citation Formats

Nelson, D E. PUREX new substation ATR. United States: N. p., 1997. Web. doi:10.2172/362456.
Nelson, D E. PUREX new substation ATR. United States. https://doi.org/10.2172/362456
Nelson, D E. 1997. "PUREX new substation ATR". United States. https://doi.org/10.2172/362456. https://www.osti.gov/servlets/purl/362456.
@article{osti_362456,
title = {PUREX new substation ATR},
author = {Nelson, D E},
abstractNote = {This document is the acceptance test report (ATR) for the New PUREX Main and Minisubstations. It covers the factory and vendor acceptance and commissioning test reports. Reports are presented for the Main 5 kV substation building, the building fire system, switchgear, and vacuum breaker; the minisubstation control building and switch gear; commissioning test; electrical system and loads inspection; electrical utilities transformer and cable; and relay setting changes based on operational experience.},
doi = {10.2172/362456},
url = {https://www.osti.gov/biblio/362456}, journal = {},
number = ,
volume = ,
place = {United States},
year = {Mon May 12 00:00:00 EDT 1997},
month = {Mon May 12 00:00:00 EDT 1997}
}