Dam overtopping risk assessment considering inspection program

  • Original Paper
  • Published:
Stochastic Environmental Research and Risk Assessment Aims and scope Submit manuscript

Abstract

Safety inspection of large dams in Taiwan is conducted every 5 years. The practice does not take into consideration uncertainty of dam conditions. The goal of this study is to determine the optimal dam inspection interval under the consideration of overtopping risk incorporating uncertainty gate availability. In earlier studies, assessment of overtopping risk only considered the uncertainties in reservoir properties and natural randomness of hydrologic events without giving much thought to the availability of spillway gates. As a result, the overtopping risk could be underestimated. In this study, an innovative concept is proposed to evaluate dam overtopping by taking into account spillway gate availability. The framework consists of three parts: (1) evaluation of conditional overtopping risk for different numbers of malfunctioning spillway gates; (2) evaluation of spillway gate availability; and (3) dam inspection scheduling. Furthermore, considerations are given to overtopping risk, inspection cost, and dam break cost for determining the optimal inspection schedule. The methodology is applied to the Shihmen Reservoir in Taiwan and to evaluate its time-dependent overtopping risk. Results show that overtopping risk considering the availability of the spillway gates is higher than the one without considering the availability of the spillway gates.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Fig. 1
Fig. 2
Fig. 3
Fig. 4
Fig. 5
Fig. 6
Fig. 7
Fig. 8
Fig. 9
Fig. 10
Fig. 11
Fig. 12
Fig. 13
Fig. 14

Similar content being viewed by others

References

  • Afshar A, Marino MA (1990) Optimizing spillway capacity with uncertainty in flood estimator. J Water Res Plan Manage ASCE 116(1):74–81

    Google Scholar 

  • Ang AHS, Tang WH (1984) Probability concepts in engineering planning and design, vol II. Decision: risk and reliability. Wiley, New York

  • Askew AJ, Yeh WGY, Hall WA (1971) Use of monte carlo techniques in the design and operation of a multipurpose reservoir system. Water Resour Res 7(4):819–826

    Article  Google Scholar 

  • Cheng ST (1993) Statistics of dam failure. In: Yen BC, Tung YK (eds) Reliability and uncertainty analysis in hydraulic design. ASCE, New York, NY, pp 97–105

    Google Scholar 

  • Cheng ST, Yen BC, Tang WH (1982) Overtopping risk for an existing dam. Civil Engineering Studies, Hydraulic Engineering Series No. 37, University of Illinois at Urbana-Champaign, Urbana, IL

  • Haimes YY, Petrakian R, Karlsson PO, Mitsiopoulos J (1988) Risk analysis of dam failure and extreme floods: application of the partitioned multiobjective risk method. IWR Report 88-R-1, Environmental Systems Management Inc., Charlottesville, VA

  • Harr ME (1989) Probabilistic estimates for multivariate analyses. Appl Math Model 13:313–318

    Article  Google Scholar 

  • Hsu YC, Kuo JT (2004) Risk and uncertainty analyses of dam overtopping: Feitsui Reservoir as a case study. In: Proceedings of the 6th intl conf on hydrosci and engr (ICHE-2004), Brisbane, Australia, paper on CD-ROM, Abstract, 459–460

  • International Commission on Large Dams (ICOLD) (1973) Lessons from dam incidents, reduced edition, Paris

  • Karlsson PO, Haimes YY (1988a) Risk-based analysis of extreme events. Water Resour Res 24(1):9–20

    Article  Google Scholar 

  • Karlsson PO, Haimes YY (1988b) Probability distributions and their partitioning. Water Resour Res 24(1):21–29

    Article  Google Scholar 

  • Karlsson PO, Haimes YY (1989) Risk assessment of extreme events: application. J Water Resour Plan Manage ASCE 115(3):299–320

    Article  Google Scholar 

  • Kuo JT, Yeh KC, Chen JH (2004) The establishment of optimal inspection interval scheduling. Department of Civil Engineering, National Taiwan University, Report submitted to Water Resources Agency, MOEA, Taiwan (in Chinese)

  • Kwon HH, Moon YI (2006) Improvement of overtopping risk evaluations using probabilistic concepts for existing dams. Stoch Environ Res Risk Assess 20(4):223–237

    Article  Google Scholar 

  • Langseth DE, Perkins FE (1983) The influence of dam failure probabilities on spillway analysis. In: Proceedings of the conf on frontiers in hydr engr, ASCE, hydr div, Cambridge, MA, 9–12 August 1983, pp 459–464

  • Meon G (1992) Overtopping probability of dams under flood load. In: Kuo JT, Lin GF (eds) Stochastic Hydraulic ’92. In: Proceedings of 6th international sym, National Taiwan University, pp 99–106

  • National Research Council (1988) Committee on techniques for estimating probabilities of extreme floods, estimating probabilities of extreme floods, methods and recommended research. National Academy, Washington, DC

    Google Scholar 

  • Pohl R (1999) Estimation of the probability of hydraulic-hydrological failure of dams. In: Proceedings of the international workshop on risk analysis in dam safety assessment, Taipei, Taiwan, pp 143–157

  • Resendiz-Carrillo D, Lave LB (1987) Optimizing spillway capacity with an estimated distribution of floods. Water Resour Res 23(11):2043–2049

    Article  Google Scholar 

  • Tang WH, Yen BC (1991) Dam safety inspection scheduling. J Hydrol Eng ASCE 117(2):214–229

    Article  Google Scholar 

  • Tung YK, Mays LW (1981) Risk models for flood levee design. Water Resour Res 17(4):833–841

    Article  Google Scholar 

  • Tung YK, Yen BC (2005) Hydrosystems engineering uncertainty analysis. McGraw-Hill Professional, New York

    Google Scholar 

  • Yeh KC, Tung YK (1993) Uncertainty and sensitivity analyses of pit-migration model. J Hydrol Eng ASCE 119(2):262–283

    Article  Google Scholar 

Download references

Acknowledgments

This study was based on the work supported by the Water Resources Agency, Ministry of Economic Affair (MOEA). The assistances from the Shihmen Reservoir Administrative Bureau and other reservoir administrative bureaus are gratefully acknowledged. We also thank the editor and referees for very helpful suggestions.

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Jan-Tai Kuo.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Kuo, JT., Hsu, YC., Tung, YK. et al. Dam overtopping risk assessment considering inspection program. Stoch Environ Res Risk Assess 22, 303–313 (2008). https://doi.org/10.1007/s00477-007-0116-3

Download citation

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s00477-007-0116-3

Keywords

Navigation