Implementasi Preventive Maintenance untuk Meningkatkan Keandalan pada Komponen Kritis Boiler di Pembangkit Listrik Tenaga Uap

Iing Pamungkas, Heri Tri Irawan, T.M. Azis Pandria

Abstract


Abstract
This paper uses a preventive maintenance approach in improving the performance reliability of critical boiler components at the Nagan Raya Steam Power Plant (PLTU Nagan Raya). PLTU currently has a strategic role in the electricity system in Indonesia, one of which is PLTU Nagan Raya, located in Aceh. In its implementation, PLTU Nagan Raya often experiences interference in its production system. The boiler is one part that often experiences interference, where corrective maintenance is one of the causes of the interference. Evaluation and performance improvement in terms of reliability is needed to minimize future failures. This research aims to determine the preventive maintenance time based on the reliability value of critical boiler components to increase the reliability value in the future. Preventive maintenance is a preventive activity before a machine breakdown occurs. The reliability value will be calculated in advance before the implementation of preventive maintenance. The implementation of preventive maintenance to increase the reliability of the nine critical components of the boiler obtained maintenance results ranging from 14 days to 47 days with a reliability value of 60%.

Keywords:
PLTU; Boiler; Reliability; Preventive Maintenance
__________________________

Abstrak

Artikel ini menggunakan pendekatan preventive maintenance dalam meningkatkan kinerja keandalan pada komponen kritis boiler di pembangkit listrik tenaga uap (PLTU) Nagan Raya. PLTU saat ini memiliki peran strategis dalam sistem ketenagalistirikan di Indonesia, dan salah satunya yaitu PLTU Nagan Raya yang terdapat di Aceh. Pada pelaksanaannya, PLTU Nagan Raya sering mengalami gangguan pada sistem produksinya. Boiler merupakan salah satu bagian yang sering mengalami gangguan, di mana pemeliharaan korektif menjadi salah satu penyebab terjadinya gangguan. Evaluasi dan peningkatan kinerja dalam hal keandalan diperlukan untuk meminimalkan kegagalan di masa mendatang. Tujuan penelitian ini untuk menentukan waktu perawatan preventif berdasarkan nilai keandalan pada komponen kritis boiler untuk meningkatkan nilai keandalan di masa yang akan datang. Preventive maintenance merupakan kegiatan pencegahan sebelum terjadinya gangguan atau kerusakan pada mesin. Nilai keandalan akan dihitung terlebih dahulu sebelum diterapkannya preventive maintenance. Hasil implementasi preventive maintenance dalam usaha peningkatan keandalan pada sembilan komponen kritis boiler didapatkan hasil pemeliharaan mulai dari 14 hari hingga 47 hari dengan perolehan nilai keandalan 60%.

Kata Kunci:
PLTU; Boiler; Keandalan; Preventive Maintenance
__________________________

Keywords


PLTU; Boiler; Reliability; Preventive Maintenance

Full Text:

PDF

References


Ebeling, C. E. (2004). An Introduction to Reliability and Maintainability Engineering. Tata McGraw-Hill Education.

Febianti, E., & Ferdinant, P. F. (2017). Peningkatkan Keandalan Mesin Main Pump Hydraulic Unit pada Lini Continuous Casting (Studi Kasus: PT. XYZ). Jurnal Teknik Industri Untirta.

Firnanda, A., & Ardiansyah, H. (2020). Analisis Kebutuhan Daya Listrik di Akademi Komunitas Negeri Aceh Barat. VOCATECH: Vocational Education and Technology Journal, 2(1), 59-66.

Jardine, A. K. S., & Tsang, A. H. C. (2013). Maintenance, Replacement, and Reliability: Theory and Applications. CRC Press.

Kumar, S., Raj, B., & Shubham, S. (2017). Study of Total Productive Maintenance & It’s Implementation Approach in Steel Manufacturing Industry: A Case Study of Equipment Wise Breakdown Analysis. International Research Journal of Engineering and Technology (IRJET), 4(8), 608–613.

Kurniawan, F. (2013). Teknik dan Aplikasi Manajemen Perawatan Industri. Graha Ilmu: Yogyakarta.

O’Connor, P., & Kleyner, A. (2012). Practical Reliability Engineering. John Wiley & Sons.

Pamungkas, I, Irawan, H. T., & Saputra, A. (2020). Risk and Reliability Analysis on Critical Components of Boiler in Steam Power Plant. IOP Conference Series: Materials Science and Engineering, 1003(1), 12048. IOP Publishing.

Pamungkas, Iing. (2019). Penentuan Tingkat Risiko dan Keandalan pada Boiler di Industri Pembangkit Listrik Nagan Raya. ETD Unsyiah.

Pamungkas, Iing, & Irawan, H. T. (2020). Strategi Pengurangan Risiko Kerusakan pada Komponen Kritis Boiler di Industri Pembangkit Listrik. Jurnal Optimalisasi, 6(1), 86–95.

Pandi, S. D., Santosa, H., & Mulyono, J. (2017). Perancangan Preventive Maintenance pada Mesin Corrugating dan Mesin Flexo di PT. Surindo Teguh Gemilang. Widya Teknik, 13(1), 33–38.

Rosa, Y. (2012). Perencanaan dan Penerapan Preventive Maintenance Peralatan Laboratorium. Jurnal Teknik Mesin, 2(2), 106–119.

Seiti, H., & Hafezalkotob, A. (2019). Developing the R-TOPSIS Methodology for Risk-Based Preventive Maintenance Planning: A Case Study in Rolling Mill Company. Computers & Industrial Engineering, 128, 622–636.

Soesetyo, I., & Bendatu, L. Y. (2014). Penjadwalan Predictive Maintenance dan Biaya Perawatan Mesin Pellet di PT Charoen Pokphand Indonesia-Sepanjang. Jurnal Titra, 2(2), 147–154.

Wang, Z., Xiao, C., Lin, X., & Lu, Y.-Y. (2018). Single Machine Total Absolute Differences Penalties Minimization Scheduling with A Deteriorating and Resource-Dependent Maintenance Activity. The Computer Journal, 61(1), 105–110.

Zhong, S., Pantelous, A. A., Goh, M., & Zhou, J. (2019). A Reliability-and-Cost-Based Fuzzy Approach to Optimize Preventive Maintenance Scheduling for Offshore Wind Farms. Mechanical Systems and Signal Processing, 124, 643–663.




DOI: https://doi.org/10.38038/vocatech.v2i2.53

Refbacks

  • There are currently no refbacks.


VOCATECH : Vocational and Technology Journal
Unit Penelitian dan Pengabdian Masyarakat & Penjaminan Mutu
Akademi Komunitas Negeri Aceh Barat
Komplek STTU Alue Peunyareng, Ujong Tanoh Darat, Meureubo, Kabupaten Aceh Barat, Aceh 23615
Telp. (0655) 7110271
Email: vocatech@aknacehbarat.ac.id


VOCATECH: Vocational Education and Technology Journal Published by:
Unit Penelitian dan Pengabdian Masyarakat & Penjaminan Mutu
Akademi Komunitas Negeri Aceh Barat


Indexed by:

GS2 logoCrossref logoGaruda logosinta-5 logosinta-5 logo

Creative Commons License logo

VOCATECH: Vocational Education and Technology Journal Creative Commons Attribution-ShareAlike 4.0 International License.