Next Article in Journal
Sustainability Impact Assessment on the Production and Use of Different Wood and Fossil Fuels Employed for Energy Production in North Karelia, Finland
Previous Article in Journal
Distributed Semantic Architecture for Smart Grids
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

An Industrial System Powered by Wind and Coal for Aluminum Production: A Case Study of Technical Demonstration and Economic Feasibility

1
School of Electrical Engineering, Wuhan University, Wuhan 430072, China
2
State Key Laboratory of Power Systems, Department of Electrical Engineering, Tsinghua University, Beijing 100084, China
3
China Power Investment Corporation, Beijing 100140, China
4
Energy Group Meng-Dong Group, Tongliao 028000, Inner Mongolia, China
*
Author to whom correspondence should be addressed.
Energies 2012, 5(11), 4844-4869; https://doi.org/10.3390/en5114844
Submission received: 8 October 2012 / Revised: 31 October 2012 / Accepted: 7 November 2012 / Published: 21 November 2012

Abstract

:
This paper presents a case study of an isolated industrial power system for aluminum production. The novel concept is that the cost of aluminum electrolysis can be significantly reduced by innovative application of hybrid systems incorporating wind energy and low-grade coal. In addition, the low-grade coal, which sale is not profitable in the market, can be locally consumed by the isolated power system. The power system thus fully utilizes the local resources in an effective and economic manner. However, several technical and economic issues are still of concern because the industrial system is isolated from the state grid. This paper hence discusses these issues and demonstrates the feasibility of such a hybrid power system from the technical and economic perspectives.

1. Introduction

The ever-increasing demand for clean energy is stimulating the worldwide installation of wind generators to drive our future society. As one of the largest energy consumers, China has its own plan to install more than 150 GW wind power by year 2020 aiming to reduce fossil energy consumption and CO2 emissions [1]. However, in China, the wind industry cannot follow the same paths of some developed countries, such as Germany and, Denmark. In these countries, the wind resources are relatively close to the load center, so most of wind power can be consumed locally [1,2,3]. In contrast, the on-shore wind resources in China are mostly concentrated in the developing western provinces, such as Gansu, Xinjiang and Inner Mongolia. The wind power generation is hence quite far away from the load centers located on the eastern coast and there are plenty of technical issues with the transmission of a large amount of wind power over long-distances [4,5]. By the end of 2009, more than half of the installed wind power has not been connected to the grid due to the lagging grid infrastructure [6,7] and the lack of appropriate grid management systems [8,9]. This represents a huge economic waste and impedes the achievement of China’s energy emission reduction targets.
To overcome the above problems, one of the solutions is off-grid technology, which enables high penetration of wind power integrated into an isolated system. The technology is quite attractive for the developing wind industry in China. Because an isolated power system does not require support from an external grid, huge investments for the construction of grid transmission systems can be avoided [10]. Some other technical issues caused by long-distance transmission can also be avoided, such as voltage instability [5] and low frequency oscillation [4], so the wind generation can be consumed locally in the western provinces of China in an effective manner. The off-grid technology is not only valuable for China, but also widely discussed in worldwide research. From the technical aspect, some published literature [11] has discussed on this topic. It has been verified to be feasible [11], stable [12], reliable [13] and flexible [14] in theory to integrate high penetration of wind power into diverse isolated systems. From the application aspect, the off-grid technology has also been adopted in some actual power systems. Reference [15] introduces the applications of off-grid technology on the Canary Islands (Spain). In this study, the integration of high percentage of wind power in the Canaries is demonstrated to be practicable based on both cost and risk analysis results. Reference [16] discusses the implementation of an isolated system located in the city of Johor Bahru (Malaysia). Seven different configurations are compared in the study and it is concluded that the hybrid energy system of PV/wind/diesel/battery only requires a reasonable investment to replace the original stand-alone diesel system and reduces the emission of CO2, especially in a high diesel price scenario. A techno-economic assessment is presented in [17,18] for an off-grid hybrid generation system located on the north-eastern part of Saudi Arabia. The assessment result demonstrates that the wind-diesel system becomes economically attractive if the carbon tax is taken into account and if diesel prices keep rising. Study [19] focuses on the electricity supply in the Brazilian Amazon Region. The authors recognize the benefits of isolated systems with wind power integrated in the Amazon Region. The off-grid technology helps to preserve the environment, whilst generating wealth and employment for the region.
In China, the primary industry sector is also the main energy consumer. During the first seven months in 2010, industrial use of electricity was 1.81 trillion kWh. Compared to the same period in 2009, it represents an increase of 22.69%, much higher than that of the tertiary industry consumption (15.39%), and that of household consumption (13.07%) [20]. Based on the aforementioned literature review, most current off-grid technologies are used for civil applications, the system capacity of which is much lower than that of industry applications. Also, most of the isolated grid is designed based on diesel generators. The start-up, as well as the power ramping rate of diesel generators is faster than that of coal-powered generators, so diesel generators are more capable of compensating wind power fluctuations in an isolated power system [21]. Considering that China is poor in oil but rich in coal [22], a wind-coal powered solution would be more suitable for China to address the wind integration issue.
This paper presents an industry project of an isolated power system located in Inner Mongolian province financed by the China Power Investment Corporation, which is one of the five largest generation corporations of China [23]. Originally, the industry system was powered by coal-fired generators for the electrolysis of aluminum, which has been categorized into the high energy consumption sector of China [24]. Due to the rapidly rising coal prices, the investor plans to integrate more wind power to control the electrolysis costs. However, the integration of wind power raises several technical and economic issues. One major technical issue, discussed in this paper, is the power balancing of this isolated system. Since the power system is distant from the inter-connected state grid, the system will reach a wind penetration level at around 47%, without any external-grid support. The power balancing of this isolated system should be carefully investigated before the construction of such a system at this high wind penetration level. Another issue is the economic aspect. With present technologies, the construction cost of wind farms is almost twice that of conventional generators [25]. The profitability of the hybrid wind-coal power system should be examined before the investment in wind generators. This paper hence discusses this economic issue. The methodology adopted is to study the investment profitability by calculating the economic indicators of “internal rate of return” and “payback period”. Through the techno-economical assessment, the isolated system is demonstrated to be both feasible and profitable. The investment will result in higher and cleaner profits from aluminum production using the presented wind-coal technologies.

2. The Industrial Power System and the Local Resources

This section gives a background review on the industrial power system and presents the motivation for the construction of additional generation capacity, as well as the integration of wind power.

2.1. Description of the Current Industry System

The power system is located in Zhahazhuoer (ZHZE), Tongliao (TL) Region, Inner Mongolian (IMo) province, which is one of China’s largest energy producing provinces thanks to its substantial energy resources [26]. This system is constructed for the power supply of an aluminum electrolysis plant, which was financed by the China Power Investment Corporation in 2006. This aluminum production stimulates the local employment and brings considerable tax-revenues for TL’s government. Therefore, in 2006 this project was regarded as one of the most important industry projects of IMo province [27]. As of 2010, the aluminum electrolysis load was around 992 MW, and total generation capacity around 1200 MW, as shown in Table 1.
Table 1. The load and generator profiles.
Table 1. The load and generator profiles.
Load NumberLoad Capacity(MW)UsageGenerator NumberGenerator Capacity (MW)
HJL#1350Aluminum ElectrolysisHJ#150
HJL#2440Aluminum ElectrolysisHJ#250
HJLH#1~#3100HeatHJ#3100
HJG#1~#8102Auxiliary PowerHJ#4100
HJ#5150
HJ#6150
HJ#7300
HJ#8300
Load in Total (MW)992 Generation in Total (MW)1200
From Table 1, the installed generation capacity is currently enough to satisfy the consumption of aluminum electrolysis and its auxiliary facilities in 2010. However, being one of the most important construction materials, aluminum consumption in China keeps increasing rapidly with the economic bloom. The China Power Investment Corporation hence plans to expand the aluminum production in order to satisfy this ever-growing market. According to the investment blueprint, another aluminum electrolysis plant has been under construction in TL region since 2011. The electrolysis plant to be completed provides an annual production capacity of 350 kton aluminum, but requires an additional 610 MW power supply according to plant specifications. This results in a gap between the power generation and demand, since the load will be increased to 1602 MW, which is much higher than the current generation capacity.
There are three possible solutions to fill the gap between the generation and demand:
  • Abandon the investment on the electrolysis plant under construction. This solution would result in an investment loss of over 4 billion RMB (6.5 RMB ≈ 1 USD) and more significantly, it reduces the investor’s competitiveness for the growing aluminum market in China.
  • Purchase electricity from state grid company. This solution requires huge investments in a transmission system since the electrolysis plant is distant away from the periphery of the state grid. In addition, the electricity price from the state grid is 0.4456 RMB/kWh. Such a high price significantly reduces the profitability of the electrolysis plant because the cost of electricity accounts for 25%–30% of the total cost for aluminum electrolysis [28].
  • Utilize local resources to satisfy the additional power demand. This solution is attractive for the investor since the utilization of local resources might also help reduce the electrolysis cost. Also, the exploitation of sustainable energy is encouraged by China’s government [1], so the investor might obtain additional tax incentive benefits from the investment. Considering TL is rich in both coal and wind resources, the investor hence carefully reviewed both resources, as discussed in the next subsections.

2.2. The Coal Resource

In ZHZE County, the amount of opencast coal reserves has been proven to be over 1740 Mton, 945 Mton of which is exploitable. Although ZHZE County is rich in coal, the local government still has set up strict policy regulations on the exploitation of coal mines due to the local environmental protection pressure. The maximum coal production is thus limited at 15 Mton/year to ensure the development of ZHZE County. With this limitation, all of the thermal coal has already been purchased through futures contracts and will be sold in the coal market in pursuit of higher profit. The isolated power system cannot purchase any more thermal coal from the local market.
Although the purchase of thermal coal is limited, low-grade coal, which is not profitable when sold into the market, is allowed to be traded freely. The isolated power system is hence able to purchase low-grade coal from the local market so as to satisfy part of the additional generation demand. However, due to the lower heating value of low-grade coal, power plants require longer coal grinding processes and extra processes in order to enhance the coal combustion, so additional auxiliary power is needed, and then the auxiliary power ratio of low-grade-coal fired power plants is raised from 8.5% to 12% of generator capacity compared with thermal coal fired power plants. This increases the unit generation cost so that low-grade-coal-powered plants are not as economic as thermal-coal-powered plants.

2.3. The Wind Resource

In addition to coal resources, ZHZE is also rich in wind resources, which can be demonstrated according to the measurements recorded by a local anemometer. As shown in Figure 1, the areas circled by “A→M” and “1→4” are two areas reserved for the potential construction of two wind farms in the future. The anemometer remarked as “#5388” is close to both areas and it records the wind speed at the heights of 10, 30, 50 and 70 m, respectively. The monthly wind speeds of ZHZE are as listed in Table 2.
Figure 1. The geographical position of anemometer “5388#”.
Figure 1. The geographical position of anemometer “5388#”.
Energies 05 04844 g001
Table 2. The monthly-average wind speed in 2009 as measured by the #5388 anemometer.
Table 2. The monthly-average wind speed in 2009 as measured by the #5388 anemometer.
HeightJANFEBMARAPRMAYJUNJULAUGSEPOCTNOVDECAverage
70 m8.918.218.517.627.927.555.436.587.656.888.128.907.67
50 m8.507.948.507.507.737.475.386.517.546.868.079.407.59
30 m8.547.848.217.267.457.235.136.247.176.497.679.037.33
10 m7.777.057.676.676.726.504.505.516.425.897.138.106.63
According to the measurement, the maximum wind speed is higher than 8 m/s in the winter season, and the minimum wind speed is higher than 6 m/s in the summer season. On average, the annual wind speed is 7.6 m/s, which corresponds to 6th level (“best-quality”) wind according to the “The wind resource assessment method of wind farms” (GB/T18710-2002) [29]. The instantaneous wind speed mainly concentrates within the valid wind speed region, which is defined between the cut-in and cut-out wind speed, normally from 3 to 25 m/s for a wind turbine. As shown by the statistical data in Table 3, there are over 7000 hrs, or 80% duration per year, in which the wind speed at 70 m is within the valid wind speed region. Thus, wind turbines can effectively produce power during most of a year.
Based on the investigation of local wind resource, it is feasible to utilize the local wind power as a main power source for the electrolysis plant. However, since wind is stochastic and intermittent, wind generators harvest energy only when wind is available. Hence, wind farms cannot fully satisfy the load demand in the low wind periods and still cannot solve the problem of generation deficiency. Thus, one practical solution is building additional low-grade-coal-fired power plants to supplement the intermittent wind power.
Table 3. The duration within the valid wind speed region.
Table 3. The duration within the valid wind speed region.
HeightHours within 3–25 m/sHours within 4–25 m/sHours within 5–25 m/s
70 m703063825776
50 m693862965692
30 m676561685524
10 m657560115406

2.4. The Wind-Coal Hybrid Energy System

A wind-coal hybrid system is hence suggested as the final solution for the power supply of the electrolysis plant. The added hybrid system includes two 400 MW wind farms located on the reserved areas shown in Figure 2 and 2 × 350 MW low-grade-coal-fired power plant as back-up for the intermittent wind generation. This solution is quite attractive for the investor because wind generation might substantially reduce the electrolysis cost considering the zero operational cost of wind. During the low wind period duration, the low-grade coal-fired generation can also fill the generation gap. The structure of this system is as shown in Figure 2, in which the yellow blocks represent the components added after the system expansion.
Figure 2. The structure of the isolated power system.
Figure 2. The structure of the isolated power system.
Energies 05 04844 g002
The characteristics of main components are briefly described as follows:
  • Coal-fired power plants. There are four coal-powered power plants. G1~G3 are thermal-coal-powered and have already been constructed. The total capacity of G1 which contains five generators HJ#1~HJ#5 is 450 MW. G2 is rated at 150 MW with only one unit, HJ#6. G3 contains two 300 MW generators numbered as HJ#7 and HJ#8 respectively. G4 is a new plant to be built for the expanded aluminum production. It has two generators: HJ#9 and HJ#10, both of which are 350 MW low-grade-coal-fired generators. These four power plants are all controlled by a central dispatch center.
  • Load. The main load in this system is aluminum electrolysis load, 1400 MW in total. Among them, HJL#1 and HJL#2 have already been constructed and HJL#3 is a new electrolysis plant under construction. The electrolysis plants are driven by DC current so they are connected with the grid through a diode-rectifier. In addition to electrolytic DC load, there are also 100 MW AC heating load and a total of 186 MW auxiliary AC power for the coal-powered power plants. In terms of auxiliary power with respect to the total power plant capacity, the ratio is 8.5% for thermal-coal-fired plants and 12% for low-grade-coal-fired plants respectively.
  • Wind Farm. Two DFIG-based wind farms are connected to this system. Each of them has 400 MW capacity. They are about to be constructed on the reserved areas as shown in Figure 1.
After the expansion on both the generation and load sides, the generation capacity will be increased to 1900 MW for coal-powered generators and the overall generation capacity is increased to 2700 MW after the wind generation is taken into account. Theoretically, such a generation capacity is enough to cover the electrolytic DC load of 1400 MW as well as the auxiliary AC load of 286 MW. However, considering the wind-load penetration will be over 800/1686 ≈ 67%, it is technically difficult to integrate such a high percentage of wind power into an isolated power system from the operational aspect. Also, in order to guarantee the investment return, the profitability of this wind-coal hybrid system should be carefully examined from the financial aspect considering the relatively higher investment for the construction of wind farms and the low-grade-coal-fired power plants. These technical and economic issues will be addressed in detail in the next sections.

3. The Technical Demonstration on the Power Balancing of the Isolated System

One major technical issue is how to maintain power balance within this isolated system. Since the power system is distant from the inter-connected state grid, the system will have a wind penetration level over 47%, but without any external-grid support. The power balancing of the proposed isolated system should be carefully investigated. This section hence discusses the technical feasibility of this proposal by analyzing the power balance in some typical meteorological scenarios.

3.1. The Controllability of System Components for Power Balancing

3.1.1. Electrolytic Load

As shown in Figure 2, the electrolytic load is connected with grid through a diode rectifier and a transformer. It is difficult to control the diode rectifier system to respond to the grid frequency variation, but the rectifier’s DC output voltage can still be adjusted by the transformer tap changer to enable the electrolytic plant to participate in the power balancing control. The secure adjustment region is as low as −10% of rated capacity according to the technical specifications provided by the manufacturer. This means that it is technically safe to reduce the electrolytic load by 1400 × 10% = 140 MW and avoid load shedding.

3.1.2. Heating Load

Heating load is temperature dependent. Normally, the peak consumption of 100 MW occurs in winter, early spring and late autumn. And in summer season, there is no requirement for supplying heat.

3.1.3. Wind Generator

With present technologies, wind generators are still “semi-participants” in power balancing control. It is because wind generators are only able to reduce the power output, but find it difficult to increase the power output due to their aerodynamic limitations [30]. Therefore, the wind generation becomes the main fluctuation source causing power imbalances in the system.

3.1.4. Coal-Fired Generator

Coal-fired generators have full capacity of participating in the power balancing control. Still, there are two limitations. Firstly, the power output must be within a valid region. The maximum output is the rated capacity and the minimum output of each generator is listed in Table 4. In total, the minimum power output should be higher than 925 MW if all the coal-powered generators are in service. Secondly, the ramping speed is limited for each generator as shown by Table 5. Ramping rate represents a unit’s power increasing capability (positive ramping) and the decreasing capability (negative ramping). In this isolated system, the ramping rate of generators should be ensured to be faster than the ramping rate of fluctuation sources, such as the wind power output, in order to keep the system power and load in balance.
Table 4. The minimum power output of generators.
Table 4. The minimum power output of generators.
Power PlantsGeneratorsCapacity (MW)Minimum output ratioMinimum power output (MW)
G1HJ#1, HJ#250 × 260%60
G1HJ#3, HJ#4100 × 260%120
G1HJ#515053.3%80
G2HJ#615053.3%80
G3HJ#7, HJ#8300 × 245%270
G4HJ#9, HJ#10350 × 245%315
In total 925
Table 5. The maximum ramping rate of generators.
Table 5. The maximum ramping rate of generators.
CapacityMaximum positive ramping rate (MW/5 min)Maximum negative ramping rate (MW/5 min)
50 MW0.92−11.25
100 MW10.00−10.00
150 MW11.67−17.50
300 MW27.50−27.50
350 MW32.10−32.10

3.2. The Investigation on Power Balancing in Extreme Scenarios

The profitability of the project strongly depends on a reliable, non-intermittent power supply to the electrolytic load. However, at a wind penetration level of 47%, any intensive wind power fluctuation might result in a system imbalance, which has been considered as one major factor that can cause load shedding or even blackouts. The power imbalance should be appropriately addressed by the coordination of the entire system. This subsection hence discusses whether the proposed wind-coal hybrid system is capable of maintaining the power balance at such a high wind penetration level.

3.2.1. Wind Power Profile

With the wind speed measurements from the “#5388” anemometer as input, the power output from the two wind farms can be roughly estimated according to the computation result from WAsP [31], which is a widely-accepted software in the field of wind farm design. The estimated power output in 2008 is plotted in Figure 3 and three special days are subsequently selected for the examination of system balance. These days include the day with the highest average output of wind power, the day with the lowest average output of wind power and the day with the highest wind power ramping rate. The system capability of maintaining power balance can be evaluated based on the investigation of these extreme scenarios.
Figure 3. The wind power output in 2008.
Figure 3. The wind power output in 2008.
Energies 05 04844 g003

3.2.2. The Day with the Highest Average Output of Wind Power

The day with the highest average wind power output is 21 December 2008. The highest wind power output also means the highest possibility that wind curtailment will occur if the entire load demand is less than the sum of wind generation and the minimum output of coal-fired generators. The purpose for selecting the day is hence on examining whether or how much the wind spillage might occur and whether the system design should be adjusted if the wind curtailment becomes unacceptable. As shown in Figure 4, the estimated load is 1686 MW in total, including 1400 MW electrolytic load, 100 MW heating load and 186 MW auxiliary power load.
Figure 4. The load profile on 21 December 2008.
Figure 4. The load profile on 21 December 2008.
Energies 05 04844 g004
The power output of wind and coal-fired generators are plotted in Figure 5 and zoomed in Figure 6. Figure 5 indicates that the wind-coal hybrid system is able to satisfy the load consumption of 1686 MW. However, since the total generation from wind and the minimum output of coal generators exceeds the total load, around 30 MW wind power should be curtailed in order to keep the system balanced as shown in Figure 6, which is a zoomed view for from 15:00 to 24:00. The curtailed wind power is only less than 30/800 = 3.75% compared to the wind farm rated capacity. The wind spillage accounts for only a little part of the entire generation capacity. This verifies that the ratio of wind generation within the hybrid system is appropriately designed.
Figure 5. The power output of wind and coal generators in 21 December 2008.
Figure 5. The power output of wind and coal generators in 21 December 2008.
Energies 05 04844 g005
Figure 6. The wind curtailment of wind farms in 21 December 2008.
Figure 6. The wind curtailment of wind farms in 21 December 2008.
Energies 05 04844 g006

3.2.3. The Day with the Lowest Average Output of Wind Power

The day with the lowest average output of wind power is 14 August 2008. The purpose of selecting the day is to examine whether the load demand can be satisfied by hybrid wind-coal generation. As shown in Figure 7, the estimated load is 1586 MW in total, including 1400 MW electrolytic load and 186 MW auxiliary power load. Heating load is not considered since the day occurs in the summer season.
Figure 7. The load profile on 14 August 2008.
Figure 7. The load profile on 14 August 2008.
Energies 05 04844 g007
Figure 8 shows that the wind-coal generation is capable of supplying the electrolysis plant. Even though there is no wind output, the coal-powered generators can still meet the overall load demand when all the generators are in service. In practice, another common scenario is that one generator is out of service due to maintenance or some other reason. The most serious situation is that the largest generator, HJ#9 of 350 MW in this paper, goes out of service. The scenario is simulated and plotted in Figure 9. According to the simulation result, a load reduction of 35 MW will ensure the system balance. The reduction of 35 MW load is within the secure adjustment region of electrolysis plant so it would not result in any load shedding events, as discussed in the first part of this section. Therefore, the simulation demonstrates that the overall capacity of coal generators is appropriately designed for the proposed wind-coal hybrid system.
Figure 8. The power output of wind and coal generators on 14 August 2008 while all generators are online.
Figure 8. The power output of wind and coal generators on 14 August 2008 while all generators are online.
Energies 05 04844 g008
Figure 9. The power output of wind and coal generators on 14 August 2008 assuming that HJ#9 generator is offline.
Figure 9. The power output of wind and coal generators on 14 August 2008 assuming that HJ#9 generator is offline.
Energies 05 04844 g009

3.3. The Day with the Highest Ramping Rate of Wind Power

The day with the highest ramping rate of wind power is 8 April 2008. The purpose for selecting the day is on examining whether the power output of coal generators can ramp fast enough to track the stochastic variation of wind power.
Figure 10. The load profile in 8 April 2008.
Figure 10. The load profile in 8 April 2008.
Energies 05 04844 g010
As shown in Figure 10, the estimated load is 1686 MW in total, including 1400 MW electrolysis load, 100 MW heating load and 186 MW auxiliary power load. Figure 11 plots the wind power output on the day of 8 April 2008 and it shows that the highest power fluctuation, which is as fast as 283 MW/5 minutes, happens from 8:50 to 9:30. When the coal generators are all in service, the overall ramping rate is fast enough to compensate for the wind power fluctuation. Figure 12 shows the power output of each generator through a calculation based on the ramping rates. According to Figure 12, the maximum ramping rate is computed for each generator as listed in Table 6, which indicates that both the positive and the negative ramping are lower than the technical limitations for all the online generators. It demonstrates that the installed generators are capable of handling the most intensive wind power fluctuation if the entire system is under normal operation.
Figure 11. The power output of wind and coal generators on 8 April 2008 while all generators are online.
Figure 11. The power output of wind and coal generators on 8 April 2008 while all generators are online.
Energies 05 04844 g011
Figure 12. The power output of coal generators on 8 April 2008 while all generators are online.
Figure 12. The power output of coal generators on 8 April 2008 while all generators are online.
Energies 05 04844 g012
Table 6. The statistics of positive/negative ramping rate while all generators are online.
Table 6. The statistics of positive/negative ramping rate while all generators are online.
CapacityMaximum positive ramping rate (MW/5 min)Maximum negative ramping rate (MW/5 min)Positive ramping rate limitation (MW/5 min)Negative ramping rate limitation (MW/5 min)
50 MW0.92–3.240.92–11.25
100 MW5.34–10.0010.00–10.00
150 MW11.67–11.6711.67–17.50
300 MW27.50–27.5027.50–27.50
350 MW32.10–32.1032.10–32.10
However, if the largest generator, HJ9#, is out of service, the overall ramping rate is not as fast as the rate of wind power variation according to the simulation results in Figure 13, Figure 14 and Figure 15. This is because the maximum positive ramping rate, as listed in Table 7, has reached the upper limit for each online generator.
Figure 13. The power output of wind and coal generators on 8 April 2008 while the HJ#9 generator is offline.
Figure 13. The power output of wind and coal generators on 8 April 2008 while the HJ#9 generator is offline.
Energies 05 04844 g013
Figure 14. The load reduction on 8 April 2008 while HJ#9 is offline.
Figure 14. The load reduction on 8 April 2008 while HJ#9 is offline.
Energies 05 04844 g014
Figure 15. The power output of other coal generators on 8 April 2008 while HJ#9 generator is offline.
Figure 15. The power output of other coal generators on 8 April 2008 while HJ#9 generator is offline.
Energies 05 04844 g015
Table 7. The statistics of positive/negative ramping rate while HJ#9 generator is offline.
Table 7. The statistics of positive/negative ramping rate while HJ#9 generator is offline.
CapacityMaximum positive ramping rate (MW/5 min)Maximum negative ramping rate (MW/5 min)Positive ramping rate limitation (MW/5 min)Negative ramping rate limitation (MW/5 min)
50 MW0.92–3.970.92–11.25
100 MW10.00–10.0010.00–10.00
150 MW11.67–15.2611.67–17.50
300 MW27.50–27.5027.50–27.50
350 MW32.10–32.1032.10–32.10
Though the available generation is limited, the isolated system can still compensate most of the wind power fluctuation and the unmet electrolysis load is about 118.7 MW, which is less than 144 MW, the maximum allowable reduction for electrolysis plant. Therefore, the most serious wind power fluctuation would only result in a temporary load reduction and a permanent load shedding or blackout event can be avoided. Considering that there is very little possibility that an intense wind fluctuation will coincide with a generator trip or maintenance on the same day, no additional generation is required for this isolated system in order to keep the overall power balance, based on the simulation results.
Through the above analysis, the power balance issue of the isolated system has been fully discussed and addressed. The entire system is demonstrated to be capable of satisfying the load demand from the electrolysis plant, in the scenarios of the highest average output, the lowest average output or the highest ramping rate wind power. Even if the largest generator is out of service, the system balance can still be maintained by a temporary load reduction of the electrolysis plant. There is very little possibility that load shedding or system blackouts will happen. Therefore, the isolated system is technically feasible to be operated under a wind penetration level at 47% and the proposed hybrid system is appropriately designed.

4. The Economic Feasibility—An Analysis of the Investment Profitability

In addition to the technical feasibility, the profitability of the project is another critical factor that affects the investment decision. Currently, the installation cost of wind generators is still higher than the conventional generators, which might reduce the investment return. Thus, the construction cost of 800 MW wind farms should be considered within the entire project investment and a full examination should be undertaken from the financial point of view. Also, the hybrid system contains six sub-systems, which will be described in Section 4.2 in details. Five of them can be operated individually. Therefore operating each of the five individual systems can be regarded as an alternative investment proposal, and the profitability of the composite system should be compared with this alternative proposal in order to verify the economic advantage of the proposed hybrid system.

4.1. Internal Rate of Return

In this paper, the internal rate of return (IRR) is selected as a main financial indicator to represent the profitability of the project. The IRR method is better at describing the profitability of an investment than the “present value” method [16] which describes the “return amount” other than the “return efficiency” of an investment. Mathematically, the IRR on an investment or project represents the "rate of return" that makes the net present value (NPV) of all cash flows (both positive and negative) from a particular investment equal to zero [32]. Given the (period, cash flow) pairs (n, Cn), the total number of periods N, and the net present value NPV, the IRR can be found from Equation (1):
N P V = n = 0 N C n ( 1 + r ) n = 0
In reference [32], a good example is also given to help understand the IRR. Based on the above description, the IRR indicator represents the “rate of return” and a higher IRR hence represents higher investment profitability. IRR is also comparable to some other economic rates, for example the nominal interest rate or the annual inflation rate. In China, the nominal interest rate and the annual inflation rate as referred in December 2011, are 3.5% [33] and 5.4% [34]. It is convenient to determine the investment profitability by comparing the computed IRR with the interest rate or the annual inflation rate to demonstrate the profitability of an investment proposal.

4.2. Parameters of the Financial Analysis of the Investment

The project includes six individual sub-systems. Two of them have been built, including the 1200 MW thermal-coal-powered power plants and 430 kTon electrolysis plant. Four of them are being evaluated, including the 2 × 400 MW wind farms, the 2 × 350 MW low-grade-coal-fired power plants, the electrolysis plant of 350 kTon annual production and a 220 kV grid infrastructure for power transmission. Except for the 220 kV grid infrastructure, the other five sub-systems can be operated individually. In this subsection, the IRR for each sub-system is calculated based on the input parameters obtained from the manufacturers. Then the different IRR values are compared with the IRR of the hybrid system for the economic feasibility study.

4.2.1. The 1200 MW Thermal-Coal-Fired Power Plants

The 1200 MW power plants have eight thermal-coal-powered generators, including 2 × 50 MW, 2 × 100 MW, 2 × 150 MW and 2 × 300 MW generators. If the power plants are operated individually, it has to sell the electricity to the state grid. The annual production of the power plants is estimated at around 5200 hours × 1200 MW = 6,240,000 MWh, and the purchased price by the state grid is expected to be 0.299 RMB/kWh. Other financial and production parameters are listed in Table 8. Taking these parameters as input, the economic indicators are computed as shown in Table 9. The asset investment of the power plant costs 5268 Million RMB at the unit construction cost of 4390 RMB/kW and the IRR of these power plants is 18.02% and the payback period is 6.47 years.
Table 8. The financial and production parameters for the 1200 MW thermal-coal-powered power plants (1 RMB ≈ 0.16 US Dollar).
Table 8. The financial and production parameters for the 1200 MW thermal-coal-powered power plants (1 RMB ≈ 0.16 US Dollar).
ItemUnitQuantity
Capital ratio%20
Loan ratio%80
Loan interest rate%5.36
Repayment periodyear15
Annual energy productionGWh3500
Auxiliary power ratio%8.5
Standard coal priceRMB/Ton300
Unit coal consumptiong/kWh317
Desulfurizer priceRMB/Ton60
Depreciation periodyear15
Residual value rate%5
Deposit rate for overhauls%2
Employee numberperson234
Average salaryRMB/year/person50,000
Average bonus rate%60
Material feeRMB/MWh6
Other feeRMB/MWh12
Table 9. The evaluation result for the 1200 MW thermal-coal-powered power plants. (1 RMB ≈ 0.16 U.S. Dollar).
Table 9. The evaluation result for the 1200 MW thermal-coal-powered power plants. (1 RMB ≈ 0.16 U.S. Dollar).
NoItemUnitQuantity
1Generation CapacityMW1200
2Asset InvestmentMillion RMB5268
3Unit Construction CostRMB/kW4390
4Internal Return of Rate%18.02
5Payback PeriodYear6.47

4.2.2. The Electrolysis Plant of 430 kTon Annual Production

The electrolysis plant provides an annual production capacity of 430 kTon. If the electrolysis plant is operated individually, it can purchase the electricity from the 1200 MW power plants at 0.299 RMB/kWh, the state grid purchase price, and sell the aluminum in the market at the price of 16,000 RMB/Ton. Other financial and production parameters are listed in Table 10. Taking these parameters as input, the economic indicators are computed as shown in Table 11. The asset investment of the electrolyzation plant is 6,595.53 Million RMB at the unit construction cost of 15,338 RMB/Ton and the IRR of the electrolysis plant is 35.32% and the payback period is 3.78 years. By comparing the same indicators, 18.02% and 6.47 years of the power plants, it is obvious that the electrolysis plant investment is more valuable than the power plants under current market conditions, so the China Power Investment Corporation is motivated to combine the self-owned power plants with the electrolysis plant in pursuit of higher profits than achievable by selling electricity to the state grid.
Table 10. The financial and production parameters for the electrolysis plant of 430 kTon annual production (1 RMB ≈ 0.16 U.S. Dollar).
Table 10. The financial and production parameters for the electrolysis plant of 430 kTon annual production (1 RMB ≈ 0.16 U.S. Dollar).
ItemUnitQuantity
Annual productionkTon430
Capital ratio%20
Loan ratio%80
Loan interest rate%5.36
Repayment periodYear15
Alumina consumptionTon/Ton1.93
Alumina costRMB/Ton3016
Electricity consumptionkWh/Ton14,250
Electricity costRMB/kWh0.299
Anode consumptionTon/Ton0.510
Anode costRMB/Ton1671
Fluoride consumptionTon/Ton0.022
Fluoride costRMB/Ton6000
Depreciation periodYear15
Residual value rate%6.33
Deposit rate for overhauls%1.5
Average salaryRMB/Ton250
Average Material feeRMB/MWh50
License feeRMB/MWh200
Management feeRMB/MWh255
Table 11. The evaluation result for the electrolysis plant of 430 kTon annual production (1 RMB ≈ 0.16 U.S. Dollar).
Table 11. The evaluation result for the electrolysis plant of 430 kTon annual production (1 RMB ≈ 0.16 U.S. Dollar).
NoItemUnitQuantity
1Annual ProductionkTon430
2Investment AmountMillion RMB6595.53
3Unit Construction CostRMB/Ton15,338
4Internal Return of Rate%35.32
5Payback PeriodYear3.78

4.2.3. The Electrolysis Plant of 350 kTon Annual Production

The electrolysis plant under evaluation in this case provides an annual production capacity of 350 kTon. If the under-built electrolysis plant is operated individually, it has to purchase the electricity from the state grid since current power generation cannot satisfy the required load demand.
Table 12. The financial and production parameters for the electrolysis plant of 350 kTon annual production (1 RMB ≈ 0.16 U.S. Dollar).
Table 12. The financial and production parameters for the electrolysis plant of 350 kTon annual production (1 RMB ≈ 0.16 U.S. Dollar).
ItemUnitQuantity
Annual productionkTon350
Capital ratio%30
Loan ratio%70
Loan interest rate%5.36
Repayment periodyear15
Alumina consumptionTon/Ton1.93
Alumina costRMB/Ton3016
Electricity consumptionkWh/Ton14,250
Electricity costRMB/kWh0.430
Anode consumptionTon/Ton0.510
Anode costRMB/Ton1671
Fluoride consumptionTon/Ton0.022
Fluoride costRMB/Ton6000
Depreciation periodyear15
Residual value rate%6.33
Deposit rate for overhauls%1.5
Average salaryRMB/Ton250
Average Material feeRMB/MWh50
License feeRMB/MWh200
Management feeRMB/MWh255
The price charged by the state grid is as high as 0.430 RMB/kWh and the price of aluminum market is still 16,000 RMB/Ton. Using the financial and production parameters as listed in Table 12, which are almost as the same as Table 10, except electricity cost, the economic indicators are computed as shown in Table 13.
Table 13. The evaluation result for the electrolyzation plant of 350k Ton annual production (1 RMB ≈ 0.16 U.S. Dollar).
Table 13. The evaluation result for the electrolyzation plant of 350k Ton annual production (1 RMB ≈ 0.16 U.S. Dollar).
NoItemUnitQuantity
1Annual ProductionkTon350
2Investment AmountMillion RMB5100
3Unit Construction CostRMB/Ton14,571
4Internal Return of Rate%5.68
5Payback PeriodYear18.60
The estimated investment costs are around 5100 Million RMB at the unit construction cost of 14,571 RMB/Ton and the IRR of the electrolytic plant is 5.68% and the payback period is 18.60 years. Obviously, the profit of aluminum electrolysis is quite sensitive to the electricity price. The indicators of this electrolysis plant are much worse than those of the 430 kTon one due to the significant increase of the electricity price. The profitability is even worse than that of the 1200 MW power plants. Thus self-owned power plants are essentially necessary to satisfy the energy demand from the electrolysis plant aimed at reducing the aluminum production cost.

4.2.4. The 2 × 400 MW Wind Farms

The 2 × 400 MW wind farms are under evaluation, and the corresponding financial and production parameters are listed in Table 14. The economic indicators are computed according to the parameters in Table 14, as shown in Table 15.
Table 14. The financial and production parameters for the 2 × 400 MW wind farms (1 RMB ≈ 0.16 U.S. Dollar).
Table 14. The financial and production parameters for the 2 × 400 MW wind farms (1 RMB ≈ 0.16 U.S. Dollar).
ItemUnitQuantity
Capital ratio%20
Loan ratio%80
Loan interest rate%6.14
Repayment periodYear15
Annual energy productionGWh1840
Depreciation periodYear15
Residual value rate%5
Employee salaryRMB/MWh9.81
Maintenance and insurance feeRMB/MWh45.65
Material feeRMB/MWh10
Other feeRMB/MWh12
Table 15. The evaluation result for the 2 × 400 MW wind farms (1 RMB ≈ 0.16 U.S. Dollar).
Table 15. The evaluation result for the 2 × 400 MW wind farms (1 RMB ≈ 0.16 U.S. Dollar).
NoItemUnitQuantity
1Generation CapacityMW800
2Investment AmountMillion RMB587,297
3Unit Construction CostRMB/kW7341
4Internal Return of Rate%13.51
5Payback PeriodYear8.81
The unit construction cost for the wind farms is 7341 RMB/kW, as listed in Table 15, which is much higher than the unit construction cost around 4300 RMB/kW for coal-fired power plants. If the wind farms sell the electricity to the state grid, the equivalent production hours are estimated at around 2300 hours, which is less than 5200 hours for coal-fired generators due to wind intermittence. Comparing Table 14 with Table 9, if the wind farms are operated individually, it is found that the profitability of wind farms are still not as good as the 1200 MW coal-fired power plants. Even though the price for wind source is zero and the price offered by the state grid is 0.510 RMB/kWh, which is much higher than the price of 0.299 RMB/kWh generated by coal power plants. Therefore it might be a more profitable option to utilize the wind generation to compensate for the power supply shortage for electrolysis load rather than to sell electricity to the state grid.

4.2.5. The 2 × 350 MW Low-Grade-Coal-Fired Power Plants

If the power plants are operated individually and sell the electricity to the state grid, the annual production is estimated at around 5000 hours × 700 MW = 3,500,000 MWh, and the purchase price by the state grid is expected at 0.314 RMB/kWh. The other financial and production parameters are listed in Table 16. Most of the parameters are similar to those of the 1200 MW power plants except the auxiliary power ratio. This parameter is 12% for low-grade-coal-fired generators but is 8.5% for the thermal-coal-fired generators. From the calculation results in Table 17 the asset investment of the power plant costs 2988.37 Million RMB at the unit construction cost of 4269 RMB/kW. The IRR for the power plant is 12.11%, which is less than that of the wind farm. Thus, the profitability for the power plant is worse than the 800 MW wind farms due to the higher auxiliary power ratio. It increases the unit generation cost so that low-grade-coal-fired plants are more suitable as backup for the wind generation and not good as the main power suppliers for aluminum production.
Table 16. The financial and production parameters for the 2 × 350 MW low-grade-coal-fired power plants (1 RMB ≈ 0.16 U.S. Dollar).
Table 16. The financial and production parameters for the 2 × 350 MW low-grade-coal-fired power plants (1 RMB ≈ 0.16 U.S. Dollar).
ItemUnitQuantity
Capital ratio%20
Loan ratio%80
Loan interest rate%6.14
Repayment periodyear15
Annual energy productionGWh3500
Auxiliary power ratio%12
Standard coal priceRMB/Ton300
Unit coal consumptiong/kWh317
Desulfurizer priceRMB/Ton60
Depreciation periodYear15
Residual value rate%5
Deposit rate for overhauls%2
Employee numberperson234
Average salaryRMB/year/person50,000
Average bonus rate%60
Material feeRMB/MWh6
Other feeRMB/MWh12
Table 17. The evaluation result for the 2 × 350 MW low-grade-coal-fired power plants (1 RMB ≈ 0.16 U.S. Dollar).
Table 17. The evaluation result for the 2 × 350 MW low-grade-coal-fired power plants (1 RMB ≈ 0.16 U.S. Dollar).
NoItemUnitQuantity
1Generation CapacityMW700
2Investment AmountMillion RMB2988.37
3Unit Construction CostRMB/kW4269
4Internal Return of Rate%12.11
5Payback PeriodYear9.2

4.2.6. 220 kV Grid Infrastructure

The investment amount of the 220 kV grid infrastructure is estimated at around 1815 Million RMB in total, including 1760 Million RMB for the transmission system and 50 MRBM for the dispatch center. The profitability of the grid will be included in the analysis of the entire system in subsection 4.2.7 since the grid infrastructure cannot return a profit by itself.

4.2.7. The Composite Isolated Power System

Using the parameters of Table 8, Table 10, Table 12, Table 14, and Table 16, the isolated power system is evaluated as a composite of the aforementioned six subsystems. The evaluation results are listed in Table 18 and compared with the result of the five sub-systems in Table 19. According to the comparison, the proposed hybrid system is more profitable than almost any of the individual systems (except the case of the electrolytic plant of 430 kTon annual production), even with the additional investment in grid infrastructure taken into account. A quick explanation of the profitability is that the intermediate procedure, selling electricity at a lower price to and purchasing at a higher price from the state grid as shown in Figure 16, is avoided by the proposed composite isolated system. The electrolysis plants are able to purchase the electricity from the self-owned coal power plants at a lower price. Further, the production cost is reduced due to the wind power integration and the final product is sold in the aluminum market, which is currently more profitable than the electricity market.
Figure 16. The intermediate procedure of the state grid (1 RMB ≈ 0.16 U.S. Dollar).
Figure 16. The intermediate procedure of the state grid (1 RMB ≈ 0.16 U.S. Dollar).
Energies 05 04844 g016
Table 18. The evaluation result for the isolated power system. (1 RMB ≈ 0.16 U.S. Dollar).
Table 18. The evaluation result for the isolated power system. (1 RMB ≈ 0.16 U.S. Dollar).
NoItemUnitQuantity
1Coal Generation CapacityMW1900
2Wind Generation CapacityMW800
3Annual aluminum productionkTon780
4Asset AmountMillion RMB27,685
5Internal Return of Rate%27.17
6Payback PeriodYear5.46
Table 19. The financial comparison between the individual subsystems and the composited system (1 RMB ≈ 0.16 U.S. Dollar).
Table 19. The financial comparison between the individual subsystems and the composited system (1 RMB ≈ 0.16 U.S. Dollar).
ItemIRR (%)Payback Period (Year)
The 1200 MW thermal-coal-fired power plants18.026.47
The 2 × 400 MW wind farms13.518.81
The 2 × 350 MW low-grade-coal-fired power plants12.119.2
The electrolytic plant of 430 kTon annual production35.323.78
The electrolytic plant of 350 kTon annual production5.6818.6
The Composite Isolated Power System27.175.46
The risk of the investment is analyzed according to a sensitivity computation. From the analysis results in Table 20, the investment return is more sensitive to the aluminum price than the investment amount and the break-even point is 14,272 RMB/Ton. The investment assumes a low risk considering the average price of aluminum from January 2010 to October 2011 was 16,250 RMB/Ton [35] and the investors are expected to remain bullish on the aluminum market with China’s rapid development.
Table 20. The sensitivity analysis on the investment risk (1 RMB ≈ 0.16 U.S. Dollar).
Table 20. The sensitivity analysis on the investment risk (1 RMB ≈ 0.16 U.S. Dollar).
Uncertainty FactorVariation (%)IRR (%)Sensitivity
Reference case027.17-
Aluminum price–105.667.92
Aluminum price1059.4111.87
Investment Amount–1036.53–3.44
Investment Amount1020.29–2.53

5. Conclusions

This paper presents a wind-coal hybrid system for aluminum production, the wind/load penetration level of which is designed as high as 47%. With such a high penetration level, this paper discusses the technical and economic issues of the isolated system. From the technical aspect, the power balance conditions of this system are studied for three different scenarios. The proposed hybrid system is demonstrated to be capable of satisfying the load demand from the electrolysis plant in the scenarios of the highest average output, the lowest average output or the highest ramping rate wind power. Therefore, the isolated system is appropriately designed to accommodate the stochastic wind power fluctuations. From the economic aspect, this paper compares the profitability of six individual sub-systems with that of the composite isolated system. Since low-grade coal and wind are produced and consumed locally, the proposed hybrid system significantly improves the profitability of the investment by maximizing the utilization of local resources and then avoiding “selling low–buying high” from the state grid. This is demonstrated by the economic comparison of the composite system with any of the individual systems. The investment in the hybrid system is hence proved as valuable and low-risk considering the state of the aluminum market.

Acknowledgement

This work was supported by the National High-Technology Research and Development Program (“863” Program) of China (2012AA050218) and by the Chinese National Natural Science Funds (51207077).

References

  1. Zhang, S.; Li, X. Large scale wind power integration in China. Analysis from a policy perspective. Renew. Sustain. Energy Rev. 2012, 16, 1110–1115. [Google Scholar] [CrossRef]
  2. Detlefsen, N.K.; Sørensen, P.E.; Eriksen, P.B. Managing Critical Weather Conditions in a LargeScale Wind Based European Power System—The Twenties Project. In Proceedings of 2011 IEEE Power & Energy Society General Meeting, Detroit, MI, USA, July 2011.
  3. Langniss, O. Incentives for grid-friendly wind power plants-examples from Spain and Germany. Presented at the Renewable Energy Grid Integration Workshop, Beijing, China, December 2010; Available online: http://www.efchina.org/csepupfiles/report/201012172020131.9655712788463.pdf/Incentives%20for%20GridFriendly%20Wind%20Power%20Plants_Ole.pdf (accessed on 24 September 2012).
  4. Fernández, R.D.; Mantz, R.J.; Battaiotto, P.E. Potential contribution of wind farms to damp oscillations in weak grids with high wind penetration. Renew. Sustain. Energy Rev. 2008, 12, 1692–1711. [Google Scholar] [CrossRef]
  5. Kocatepe, C.; İnan, A.; Arıkan, O.; Yumurtaci, R.; Kekezoğlu, B.; Baysal, M.; Bozkurt, A.; Akkaya, Y. Power quality assessment of grid-connected wind farms considering regulations in turkey. Renew. Sustain. Energy Rev. 2009, 13, 2553–2561. [Google Scholar] [CrossRef]
  6. Lin, J.; Sun, Y.Z.; Sørensen, P. Model for assessing grid frequency deviation due to wind power fluctuation base on “time-frequency” transformation. IEEE Trans. Sustain. Energy 2012, 3, 65–73. [Google Scholar] [CrossRef]
  7. Lin, J.; Sun, Y.Z.; Cheng, L.; Gao, W.Z. Assessment of the power reduction of wind farms under extreme wind condition by a high resolution simulation model. Appl. Energy 2012, 96, 21–32. [Google Scholar] [CrossRef]
  8. Zhen, Y.Z.; Ji, H.; Jian, Z. Performance of wind power industry development in China: A diamond model study. Renew. Energy 2009, 34, 2883–2891. [Google Scholar] [CrossRef]
  9. Zhang, D.; Zhang, X.; He, J.; Chai, Q. Offshore wind energy development in China: Current status and future perspective. Renew. Sustain. Energy Rev. 2011, 15, 4673–4684. [Google Scholar] [CrossRef]
  10. Kaundiny, D.; Balachandra, P.; Ravindranath, N.H. Grid-connected versus stand-alone energy systems for decentralized power—A review of literature. Renew. Sustain. Energy Rev. 2009, 13, 2041–2050. [Google Scholar] [CrossRef]
  11. Luo, C.; Ooi, B.T. Frequency deviation of thermal power plants due to wind farms. IEEE Trans. Energy Convers. 2006, 21, 709–716. [Google Scholar] [CrossRef]
  12. Banakar, H.; Luo, C.; Ooi, B.T. Impacts of wind power minute-to-minute variations on power system operation. IEEE Trans. Power Syst. 2008, 23, 150–160. [Google Scholar] [CrossRef]
  13. Erdinc, M.U. Optimum design of hybrid renewable energy systems: Overview of different approaches. Renew. Sustain. Energy Rev. 2012, 16, 1412–1425. [Google Scholar] [CrossRef]
  14. Ribeiro, L.A.S.; Osvaldo, R.S.; Lima, S.L.; Matos, J.G. Isolated Micro-Grids with renewable hybrid generation: The case of Lençóis island. IEEE Trans. Sustain. Energy 2011, 2, 1–11. [Google Scholar] [CrossRef]
  15. Marrero, G.A.; Ramo, F.J. Electricity generation cost in isolated system: The complementarities of natural gas and renewables in the Canary Islands. Renew. Sustain. Energy Rev. 2010, 14, 2808–2818. [Google Scholar] [CrossRef]
  16. Ngan, M.S.; Tan, C.W. Assessment of economic viability for PV/wind/diesel hybrid energy system in southern Peninsular Malaysia. Renew. Sustain. Energy Rev. 2012, 16, 634–647. [Google Scholar] [CrossRef]
  17. Rehman, S.; Alam, M.M.; Meyer, J.P.; Al-Hadhrami, L.M. Feasibility study of a wind and diesel hybrid power system for a village. Renew. Energy 2012, 38, 258–268. [Google Scholar] [CrossRef]
  18. Rehman, S.; El-Aminb, I.M.; Ahmad, F.; Shaahid, S.M.; Al-Shehri, A.M.; Bakhashwain, J.M.; Shash, A. Feasibility study of hybrid retrofits to an isolated off-grid diesel power plant. Renew. Sustain. Energy Rev. 2007, 11, 635–653. [Google Scholar] [CrossRef] [Green Version]
  19. Andrade, C.S.; Ros, L.P.; Silv, N.F. Generation of electric energy in isolated rural communities in the Amazon Regional proposal for the autonomy and sustainability of the local populations. Renew. Sustain. Energy Rev. 2011, 15, 493–503. [Google Scholar] [CrossRef]
  20. China’s electricity consumption up in July. China Daily. 14 August 2010. Available online: http://www.chinadaily.com.cn/china/2010-08/14/content_11154130.htm (accessed on 24 September 2012).
  21. Risø National Renewable Energy Laboratory. The Intelligent Energy System Infrastructure for the Future; Technical Report Risø-R-1695 (EN). Risø National Renewable Energy Laboratory: Roskilde, Denmark, September 2009. Available online: http://130.226.56.153/rispubl/reports/ris-r-1695_uk_summ.pdf (accessed on 24 September 2012).
  22. Ma, H.; Oxley, L.; Gibson, J. China’s energy situation in the new millennium. Renew. Sustain. Energy Rev. 2009, 13, 1781–1799. [Google Scholar] [CrossRef]
  23. Wikipedia. China Power Investment Corporation. Available online: http://en.wikipedia.org/wiki/China_Power_Investment_Corporation (accessed on 24 September 2012).
  24. National Development and Reform Commission. The Notice on the Tariff Concession Cancellation of the Aluminum High-Energy-Consuming Industries; National Development and Reform Commission: Beijing, China, 2007. Available online: http://www.sdpc.gov.cn/zcfb/zcfbtz/2007tongzhi/t20080222_193192.htm (accessed on 24 September 2012).
  25. British Petroleum, BP. The Cost of Generating Electricity: A Study Carried out by BP Power for the Royal Academy of Engineering; The Royal Academy of Engineering: London, UK, 2004; Available online: http://www.raeng.org.uk/news/publications/list/reports/Cost_of_Generating_Electricity.pdf (accessed on 24 September 2012).
  26. Wikipedia. Inner Mongolian. Available online: http://en.wikipedia.org/wiki/Inner_Mongolia (accessed on 24 September 2012).
  27. CPI Energy Group Meng-Dong Group. Meng-Dong Group Introduction. Available online: http://www.zdhm.com.cn/recruitmentContent-47.shtml (accessed on 24 September 2012).
  28. Men, C. Analysis and forecast of Aluminum market. Light Medal. 2003, 11, 3–7. [Google Scholar]
  29. Chinese Standard Bureau. The Wind Resource Assessment Method of Wind Farms; GB/T18710-2002; General Administration of Quality Supervision, Inspection and Quarantine: Beijing, China, 2002. [Google Scholar]
  30. Hansen, A.D.; Sørensen, P.; Iov, F.; Blaabjerg, F. Centralised power control of wind farm with doubly fed induction generators. Renew. Energy 2006, 31, 935–951. [Google Scholar] [CrossRef]
  31. WAsP. User Manual. Available online: http://www.wasp.dk/?sc_lang=en (accessed on 24 September 2012).
  32. Wikipedia. Internal Rate of Return. Available online: http://en.wikipedia.org/wiki/Internal_rate_of_return (accessed on 24 September 2012).
  33. Bank of China. Deposit Interest Rate. Available online: http://www.boc.cn/finadata/lilv/fd31/201107/t20110706_1444098.html (accessed on 24 September 2012).
  34. National Bureau of Statistics of China. CPI Indicator. Available online: http://www.stats.gov.cn/was40/gjtjj_detail.jsp?searchword=5.4%25&channelid=6697&record=1 (accessed on 24 September 2012).
  35. Global Metal Network. Aluminum Price. Available online: http://www.ometal.com/historydata/view.asp?m=5&__tmp=200&t=201&syear=2010&smonth=01&eyear=2011&emonth=10 (accessed on 24 September 2012).

Share and Cite

MDPI and ACS Style

Sun, Y.-Z.; Lin, J.; Song, Y.-H.; Xu, J.; Li, X.-M.; Dong, J.-X. An Industrial System Powered by Wind and Coal for Aluminum Production: A Case Study of Technical Demonstration and Economic Feasibility. Energies 2012, 5, 4844-4869. https://doi.org/10.3390/en5114844

AMA Style

Sun Y-Z, Lin J, Song Y-H, Xu J, Li X-M, Dong J-X. An Industrial System Powered by Wind and Coal for Aluminum Production: A Case Study of Technical Demonstration and Economic Feasibility. Energies. 2012; 5(11):4844-4869. https://doi.org/10.3390/en5114844

Chicago/Turabian Style

Sun, Yuan-Zhang, Jin Lin, Yong-Hua Song, Jian Xu, Xiao-Ming Li, and Jian-Xun Dong. 2012. "An Industrial System Powered by Wind and Coal for Aluminum Production: A Case Study of Technical Demonstration and Economic Feasibility" Energies 5, no. 11: 4844-4869. https://doi.org/10.3390/en5114844

Article Metrics

Back to TopTop