Urban planning and rail transport risks: Coping with deadlocks in Dutch urban development projects

https://doi.org/10.1016/j.ssci.2013.01.025Get rights and content

Abstract

Due to recent disasters and near misses, society has become more aware of the risks involved in the production, storage and transport of hazardous materials. In the Netherlands, this has led to more attention for the institutionalisation of risk management approaches in order to prevent disasters and improve the safety of people in areas adjacent to risky activities. However, this institutionalisation of risk management concerning rail transport of hazardous materials has led to a number of problems for urban planning and even deadlocks in decision making. In order to unlock these situations, an unfreezing and reframing of decision making is necessary. This article explores the potential impact of an adapted institutional view on decision making, based on empirical research.

Highlights

► Institutionalisation of risk management has led to deadlocks in decision making. ► We examine the influence of an adapted institutional framework on decision making. ► We performed two gaming simulations in real world cases experiencing a deadlock. ► The adapted framework led to a different outcome of decision making. ► Respondents involved agreed the new outcome was an improvement compared to practice.

Introduction

The general debate on involuntary risks has intensified since the 1980s. In the Netherlands, this is due to some large incidents among which the crash of a Boeing aircraft in a large apartment building in Amsterdam in 1992 with 43 casualties among residents and the explosion of the SE Fireworks production plant destroying a complete neighbourhood in the city of Enschede in 2000, killing 23 people. Risks related to rail transport of hazardous materials received particular public attention after several near misses with freight trains in the cities of Tilburg (2007) and Barendrecht (2009, 2011) for example. Moreover, De Wilde (2006) argues that more than in other European countries, rail transport of hazardous materials in the Netherlands is organised right through city centres, creating a strong interaction between rail transport, urban planning and the (re)development of real estate near railways. However, this growing Dutch awareness is not unique. Other disasters involving hazardous materials have occurred internationally in recent years. The city of Viareggio (Italy) experienced a so-called vapour cloud explosion after a derailment discharged liquefied petroleum gas (LPG) from a tank wagon in June 2009, causing 27 casualties.

Due to these disasters, society has become more aware of the risks involved in the production, storage and transport of hazardous materials. In the Netherlands, this has led to more attention for the institutionalisation of risk management approaches in order to prevent disasters and improve the safety of people in areas adjacent to risky activities. This is formalised in what is known in the Netherlands as external safety policy. External safety policy aims to control the risks related to the production, storage and use of hazardous materials (for instance: fireworks, liquefied petroleum gas, ammunition), the transport of hazardous materials by road, rail or water and through pipelines, and the use of airports (Ministerie van VROM, 2006). The basis for the Dutch external safety policy is constituted by generic norms for acceptable external safety levels.

The first way to describe risk is in terms of individual risk (IR) (see Fig. 1). This is the annual probability that an unprotected person will die as a result of an accident involving hazardous materials at a certain spot if that person resides there for a full year. The risk is visualised on a map by dots interpreted as spatial contours. The maximum allowed risk for ‘new’ situations as laid down in Dutch law is 1 * 10−6.

The second way to describe risk is in terms of group risk (GR) (see Fig. 2). This is the cumulative probability for each year that at least 10, 100 or 1000 people die as a direct result of their presence in the influence area of an establishment or transport route if an incident happens with hazardous materials. This is visualised on a logarithmic scale by using the fN curve, where f represents the frequency of an accident and N the number of people expected to die as a result of that accident.

It should be noted that there are of course more ways to conceptualise risks, such as in economic loss, catastrophic potential or the number of potential injuries. Dutch safety institutions however, have a very strong emphasis in the number of potential casualties. Therefore, in the following we will also elaborate on the number of potential casualties instead of other potential risk criteria.

In the Netherlands the issue of rail transport of hazardous materials in interaction with urban planning receives relatively much attention. According to an Environmental Resources Management (ERM) study (2005), the approach to risk management in the Netherlands is unique to some extent due to its strong focus on the fore mentioned generic standards. Moreover, Dutch authors stress the differences between the Netherlands and other countries due to some unique spatial characteristics. Perhaps because of this somewhat distinctive position of the Netherlands in this respect, almost only Dutch authors seem to explicitly address external safety in relation to urban planning. Suddle, 2004, Suddle, 2006, Suddle, 2008, van der Vlies and Suddle, 2008, for example, focuses on measures to reduce the possible impact of disasters on the built environment, whereas research performed by Ale, 2002, Ale, 2003, Ale, 2005 focuses more on the performance of risk institutions in the Netherlands. In contrast, authors from a variety of nations focus on quantitative aspects of release of toxins or quantitative aspects of routing. Examples of the latter are Glickman and Rosenfield, 1984, Verter, 1998, Leonelli et al., 2000, Høj and Kröger, 2002, Verma and Verter, 2005. Also, this does not imply that there are no similarities concerning risk management. In Europe, the Seveso directive aims to improve the safety of sites containing large quantities of dangerous substances and strategies for urban planning to improve safety (see for example Cahen, 2006 or Basta, 2009).

The considerable attention to the issue of transport and external safety resulted in a unique document published in 2003 by the Dutch National Advisory Boards on Transport and Spatial Planning on the (problems with the) integration of external safety policy, transport policy and urban and regional planning (Raad voor Verkeer en Waterstaat en de Vromraad, 2003). In this report an analysis is given of the trends, the complex institutional contexts and the problems of integrated policy development at different governmental levels. The report warns for future incidents and calls for innovative (mainly institutional) solutions. In a recent study (van der Vlies, 2011), initiated in reaction to this 2003 report of the advisory boards, some possible approaches for improvement were explored. The study mainly focused on the structure and impacts of relevant institutions in relation to the rail transport of hazardous materials in connection with local urban developments. It was hypothesised that the present institutions to some degree create an obstacle for finding good solutions for the tensions between the transport domain and the urban planning domain, tensions that often result in policy deadlocks in decision making in day-to-day reality. Changing the institutions might be helpful for unfreezing these deadlocks, reframing the local debate and finding attractive and widely supported solutions.

This article aims to present some of the findings of this study. The structure is as follows. In Section 2, the main problems with decision making in relation to the institutional setting are summarised, based on the exploration using different methods by van der Vlies (2011). In Section 3 an adapted view on rail transport risks management in relation to urban development will be presented. The impacts of this adapted view are explored in an experimental context using simulation games. The set up are described in Section 4, the main results in Section 5. The article ends in Section 6 with conclusions and a brief discussion on the results.

Section snippets

The institutional problem

The first part of the study of van der Vlies (2011) explores the problems of decision making on urban development in areas adjacent to railways accommodating hazardous material transport. Three methods were applied: document analysis, a study of six cases in Dutch cities and workshops with experts from practice. Based on these analyses, six different problem categories in the practice of decision making are identified.

The first category concerns problems related to risk modelling. In practice,

Towards an alternative approach

Based on the analysis summarized in Section 2, there are three main goals for planning and decision-making identified which should be pursued with an adapted view. The first goal is to enrich the process of the management of risks related to urban planning in areas facing transport of hazardous materials. For unfreezing deadlocks, a shift is needed from the traditional focus on finding the optimal solution to a focus on a satisfactory solution, taking into account local unique circumstances.

Test goals

In order to explore the potential impact of the adapted institutional view, we set up a test to investigate whether the hypothesised effect of unfreezing and reframing of deadlock situations in local urban development can be observed in real-world situations with real world planners and decision makers. Hence, the overall goal of the test is to gain insight into whether the adapted institutional view will, as hypothesised, improve the quality of the decision making process related to urban

The first gaming simulation: Roosendaal

Before the simulations were performed, the major characteristics of the area were modelled in URBIS EV. The modelling was based on population files from an earlier national risk evaluation from 2005 called the Anker Project. These population files proved to be less accurate than they should be, which in the end appeared to have some influence on the outcome of the game.

Seven people participated in the gaming simulation in Roosendaal, of whom two were from private real estate developers, the

Conclusions and discussion

This article developed an adapted view on the institutional rules that govern the planning and decision making processes for urban development projects adjacent to railways accommodating transport of hazardous materials. The need for such an adapted view was argued from various observations in The Netherlands on the presence and the continuation of problems with meeting external safety standards in present situations. To test the value of the adapted view, a gaming simulation approach for two

References (39)

  • K.M. Eisenhardt

    Building theories from case study research

    Academy of Management Review

    (1989)
  • ERM (Environmental Resources Management), 2005. Comparing notes: Opportunities for Learning and Co-operation in...
  • S. Geertman

    Potentials for planning support: a planning-conceptual approach

    Environment and Planning B: Planning and Design.

    (2006)
  • J.L.A. Geurts et al.

    Changing Organisations with Gaming/Simulation

    (2000)
  • T.S. Glickman et al.

    Risks of catastrophic derailments involving the release of hazardous materials

    Management Science

    (1984)
  • G. Kuiper

    Compensation of environmental degradation by highways: a Dutch case-study

    European Environment

    (1997)
  • Ministerie van Infrastructuur en Milieu, 2011. Handleiding Risicoanalyse Transport. Concept versie 1 november 2011....
  • Ministerie van Verkeer en Waterstaat, 2004. Nota mobiliteit: naar een betrouwbare en voorspelbare bereikbaarheid, Den...
  • Ministerie van Verkeer en Waterstaat, 2006. Nota vervoer gevaarlijke stoffen, Den...
  • Cited by (6)

    • Using an evidence-based safety approach to develop China's urban safety strategies for the improvement of urban safety: From an accident prevention perspective

      2022, Process Safety and Environmental Protection
      Citation Excerpt :

      According to the analysis in Section 3, many urban accidents occur because of the unsafe urban infrastructure in China, so urban infrastructure safety management should be an important aspect of urban safety management. To strengthen urban infrastructure safety management, the following strategies are proposed: (1) adhering to safety in the first instance in urban infrastructure construction (SAWS, 2017a); (2) constructing the urban underground pipe network by adopting the mode of the utility tunnel (Xu et al., 2013; SAWS, 2014); (3) strengthening the construction of urban infrastructure related to the traffic, water supply, drainage, waterlogging, heat supply, sewage, sludge, and garbage disposal, etc. (MHURC of the PRC, and NDRC of the PRC, 2017; SC of the PRC, 2018a); (4) building a special safety management platform for important urban infrastructures related to the power supply, water supply, drainage, gas supply, roads and bridges, underground engineering, etc. (Huang et al., 2017); (5) strengthening safety monitoring and control of concealed facilities and waste disposal sites (Ouyang et al., 2016; SAWS, 2017b; Zhan et al., 2018); (6) strengthening the safety supervision and management in the operation process of urban infrastructures, as well as the construction, replacement, and upgrading of safety infrastructure for municipal facilities; (7) strengthening the construction and maintenance of fire safety facilities (e.g., firehouses, fire water sources, etc.) to shorten the response time of fire-extinguishing (General Office of the SC of the PRC, 2017b; Xinhua News, 2015; Xinhua News, 2017; Zhejiang Administration of Work Safety, 2017; Department of Emergency Management Heilongjiang Province, 2019); (8) speeding up the elimination of railway level-crossing in urban densely-populated areas (Vlies and Heijden, 2013; SC of the PRC, 2018b); (9) optimizing the urban road network and traffic organization, improving the management of road safety facilities (Lyu et al., 2022), such as scientifically and standardly providing road safety facilities, and improving safety facilities for the pedestrians crossing the street; (10) strengthening the safety supervision and management in the reconstruction process of urban shantytowns, urban villages and dangerous buildings; and (11) strictly regulating and controlling the illegal construction of urban built-up areas (SAWS, 2017a). According to the analysis in Section 3, some high-risk industries (e.g., dangerous chemical industries, as well as firework and firecracker industries) seriously threaten urban safety.

    • HazMat transportation safety assessment: Analysis of a “Viareggio-like” incident in the Netherlands

      2020, Journal of Loss Prevention in the Process Industries
      Citation Excerpt :

      During transportation, accidents may occur and propagate among tankers leading to severe fires, explosion or toxic dispersions (Casal, 2018). This may increase the level of individual and societal risk associated to those activities, since the transport network often crosses densely populated areas (Jardine et al., 2003; Ryland, 1999; van der Vlies and van der Heijden, 2013). Due to the relevant safety issues posed by HazMat transportation, the scientific community devoted several efforts to develop quantitative tools for risk assessment of this specific activity.

    • Back on track: Creating a robust institutional framework for rail transport of hazardous substances in the Netherlands

      2018, Safety Science
      Citation Excerpt :

      External safety policy aims to control the risks related to the production, storage and use of hazardous substances, as well as the transport of hazardous substances by road, rail or water and through pipelines, and the use of airports (Ministerie van VROM, 2006a). The risks related to rail transport of hazardous substances received particular public attention after several near misses with freight trains in the cities of Delfzijl (2000), Amersfoort (2002), Tilburg (2007, 2015) and Barendrecht (2011) (see Van der Vlies and Van der Heijden, 2013). An accident with a Dutch train carrying hazardous substances in Wetteren, Belgium (2013) also created much attention for this subject.2

    • Robustness assessment of urban rail transit based on complex network theory: A case study of the Beijing Subway

      2015, Safety Science
      Citation Excerpt :

      Therefore, a better understanding of the topological characteristics of rail transit systems is crucial for improving the robustness of them against both inside disruptions and outside attacks (Crucitti et al., 2003; Derrible and Kennedy, 2010; Kyriakidis et al., 2012; Wu et al., 2008). The increasing availability of data acquisition on large systems and the rapid development of artificial intelligence techniques aided by computer technology (Vernez and Vuille, 2009; Zhao et al., 2012; Zhong et al., 2010) have led to great advances in our understanding of the topological complexity of critical infrastructures (Ding et al., 2014; Glickman and Erkut, 2007; van der Vlies and van der Heijden, 2013; Zhang et al., 2014). In spite of the significance, the study of these critical infrastructures is an essentially complicated issue since they are continuously growing in complexity and heterogeneity, which makes a single modeling unreliable in this case.

    View full text