A practical approach to resource - constrained project scheduling

  • Published:
Operational Research Aims and scope Submit manuscript

Abstract

In this paper a solution approach is discussed for managing projects with resource constraints. For this purpose a heuristic method is developed based on traditional CPM scheduling calculations and leveling algorithms. The method can be applied using normal scheduling software such as P3 and MS project, and as such, it is of value to practitioners. An illustrative example is also presented herein to exemplify the concepts. The problem solved has importance and direct application to the management of a wide variety of project-structured efforts with prevailing resource constraints.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

References

  • Abeyasinghe, M.C., Greenwood, D.J. and Johansen, D.E. (2001). An efficient method for scheduling construction projects with resource constraints, International Journal of Project Management, 19(1), pp. 29–45.

    Article  Google Scholar 

  • Ahuja, H., Dozzi, S.P. and AbouRizk, S.M. (1994). Project management techniques in planning and controlling construction projects, 2nd edition, Wiley, New York.

    Google Scholar 

  • Burgess, A.R. and Killebrew, J.R. (1962). Variation in activity level on a cyclical arrow diagram, Journal of Industrial Engineering, 13(2), pp. 76–83.

    Google Scholar 

  • Davis, E.W. and Heidorn, G.E. (1971). An algorithm for optimal project scheduling under multiple resource constraints, Management Science, 27(2), pp. 803–816.

    Google Scholar 

  • Davis, E.W. and Patterson, J.H. (1975). A comparison of heuristic and optimum solutions in resource constrained project scheduling, Management Science, 21, pp. 944–955.

    Article  Google Scholar 

  • Dorndorf, U., Pesch, E. and Phan-Huy, T. (2000). A time-oriented branch-and-bound algorithm for resource-constrained project scheduling with generalised precedence constraints, Management Science, 46(10), pp. 1365–1384.

    Article  Google Scholar 

  • Galbreath, R.V. (1965). Computer program for leveling resource usage, Journal of Construction Division, ASCE, 91(1), pp. 107–124.

    Google Scholar 

  • Garey, M.R., Graham, R.L., Johnson, D.S. and Yao, C. (1976). Resource constrained scheduling as generalized bin packing, Journal of Combinatorial Theory, (A)21, pp. 257–298.

    Article  Google Scholar 

  • Goldratt, E.M. (1997). Critical chain, The North River Press.

  • Harris, R.B. (1978). Precedence and Arrow Network for Construction, Wiley.

  • Harris, R.B. (1990). Packing method for resource leveling, Journal of Construction Management, ASCE, 61(2), pp. 331–351.

    Article  Google Scholar 

  • Hegazy, T. (1999). Optimization of resource allocation and leveling using genetic algorithm, Journal of Construction Engineering and Management, ASCE, 125(3), pp. 167–175.

    Article  Google Scholar 

  • Herroelen, W., Reyck, B.D. and Demeulemeester, E. (1998). Resource-constrained project scheduling: a survey of recent developments, Computers and Operation Research, 25(4), pp. 179–302.

    Article  Google Scholar 

  • Kaplan, L. (1988). Resource-constrained project scheduling with preemption of jobs, Ph.D. Thesis, University of Michigan, Ann Arbor, U.S.A.

    Google Scholar 

  • Khattab, M.M. and Choobineh, F. (1991). A new heuristic for project scheduling with a single resource constraint, Computers and Industrial Engineering, 20, pp. 381–387.

    Article  Google Scholar 

  • Kumar, V.K.A. and Rajendran, C.R. (1993). Manpower resource leveling in the maintenance of drillship: a computer simulation approach, International Journal of Modelling and Simulation, 13(4), pp. 152–155.

    Google Scholar 

  • Lee, Y. and Gatton, T.M. (1994). Construction scheduling based on resource constraints, AACE Transactions, 3, pp. 1–6.

    Google Scholar 

  • Leu, S. and Yang, C. (1999). GA-based multicriteria optimal model for construction scheduling, Journal of Construction Engineering and Management, 125(6), pp. 420–427.

    Article  Google Scholar 

  • Leu, S., Chen, A. and Yang, C. (1999). Fuzzy optimal model for resource-constrained construction scheduling, Journal of Computing in Civil Engineering, 13(3), pp. 207–216.

    Article  Google Scholar 

  • Lu, M. and Li, H. (2003). Resource-activity critical path method for construction planning, Journal of Construction Engineering and Management, 129(4), pp. 412–420.

    Article  Google Scholar 

  • Moder, J.J., Phillips, C.R. and Davis, E.W. (1983). Project Management with CPM, PERT, and Precedence Diagramming, 3rd edition, Van Nostrand Reinhold, New York.

    Google Scholar 

  • Turnquist M. A. and Nozick, L.K. (2003). Allocating time and resources in project management under uncertainty. Proceedings of the 36th Hawaii International Conference on System Sciences (HICSS’03), Vol. 1, pp 187–195.

    Google Scholar 

  • Wiest, J.D. (1964). Some properties of schedules for large projects with limited resources, Operational Research, 12(3), pp. 395–418.

    Google Scholar 

  • Willis, R.J., H. Pan and C.-H. Yeh (1999). Resource-constrained project scheduling under uncertain activity duration, in Computational Intelligence for Modelling, Control & Automation, M. Mohammadian (ed.), IOS Press, Amsterdam, pp. 429–434.

    Google Scholar 

  • Yang, B., Geunes, J. and O’Brien, W.J. (2001). Resource-constrained project scheduling: Past work and new directions, Research report 2001-6, Department of Industrial and Systems Engineering, Univerity of Florida.

  • Yeh, C.-H., H. Pan and R.J. Willis (1999). A heuristic approach to fuzzy resourceconstrained project scheduling, in Computational Intelligence for Modelling, Control & Automation, M. Mohammadian (ed.), IOS Press, Amsterdam, pp. 423.

    Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Rights and permissions

Reprints and permissions

About this article

Cite this article

Pantouvakis, JP., Manoliadis, O.G. A practical approach to resource - constrained project scheduling. Oper Res Int J 6, 299–309 (2006). https://doi.org/10.1007/BF02941258

Download citation

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF02941258

Keywords

Navigation